House Restoration Update
Here's how our house is coming:
flooring contractor: hired
vinyl for 3 bathrooms: ordered
upstairs carpet: Friese carpet ordered
drywall repair: Joe has it half-way done
crown moulding: purchased
plumbing: 3 new toilets purchased
checks from insurance company: hopefully on their way
Next steps:
finish drywall, texture and paint
paint and install crown moulding
have vinyl installed
install toilets
touch-up wall paint in damaged areas
move furniture out of upstairs
have carpet installed
replace all removed baseboard mouldings
have downstairs carpet cleaned
flooring contractor: hired
vinyl for 3 bathrooms: ordered
upstairs carpet: Friese carpet ordered
drywall repair: Joe has it half-way done
crown moulding: purchased
plumbing: 3 new toilets purchased
checks from insurance company: hopefully on their way
Next steps:
finish drywall, texture and paint
paint and install crown moulding
have vinyl installed
install toilets
touch-up wall paint in damaged areas
move furniture out of upstairs
have carpet installed
replace all removed baseboard mouldings
have downstairs carpet cleaned
Comments